Waste Water Pump Station 126

Client: 

Downer

Consultant: 

SCIRT

Contract value: 

$370,000

Duration: 

11 Weeks

Brief: 

Construct waste water pumping station 126 on Maunsell Street

Scope: 

  • Temporary works consisting of a sheet piled cofferdam of 5m x 5m with 8m deep FSPIII sheet piles driven 1m below the existing ground level and well point dewatering to allow excavation to 6.7m
  • Earthworks involving bulk excavation 320m3 and subsequent filling of 240m3
  • Structural concrete works for foundations, retaining and finishing slabs.
  • Installation of concrete wet well and valve chamber structures along with all mechanical pipework and valving.
  • Installation of the out falling pressure main and pumping station bypass assembly.
  • Construction of electrical control kiosk foundation and ducting.